Canutillo ES

Key Information

  • Safety & Security Upgrades
  • Technology Upgrades
  • New Rooftop Units
  • New Roof & Repairs to Parapets
  • New Instructional Technology
Design Process
Construction Process
Canutillo Elementary School, Canutillo Avenue, Canutillo, TX, USA
Budget
$9,508,562
Construction Starts
August 2025
Anticipated Completion
July 2026

Project Team

Ernie Ortiz
Program Director
Alec Kleinhans
Owner’s Representative
Contractor
Banes General Contractors
Architect
GA Architecture Inc.

Project Updates

Subscribe to emails with updates for this project. You’ll receive a verification email after your first project sign-up.
09/18/2025
Bond Renovations Continue with Groundbreaking at CES!

Canutillo ISD, community members, and students gathered at Canutillo Elementary to celebrate the start of renovations funded by the 2024 Canutillo Bond. This marks the 5th groundbreaking of six renovation projects scheduled to begin this year, as part of the $387 million CISD bond.

The $9.5 million project will focus on new entry vestibules designed to control campus access, advanced security cameras, modernized communication systems, a new fire alarm and badge-controlled door access. The project will also bring new HVAC units, roofing and flooring along with fresh exterior paint.

The project was designed by GA Architecture and is being built by Banes General Contractors.

Additional groundbreaking events will continue throughout the fall as CISD and Procedeo deliver on the community’s vision to transform learning environments across the district.